Dodd Blvd./Flagstaff Ave. Intersection Improvement Project

The City of Lakeville and Dakota County are partnering to construct a single-lane roundabout at the intersection of Dodd Boulevard and Flagstaff Avenue to improve intersection operations, make safety improvements and provide for increasing traffic levels. Design work on the project is ongoing. The construction contract is anticipated to be awarded in March 2019 with construction starting in June and finishing sometime in the fall.

The proposed improvements required the acquisition of a single-family property at the northwest corner of Dodd Boulevard and Flagstaff Avenue. Demolition of the home will be completed this winter.

Helpful Documents


Proposed Project Timeline


  • Preliminary engineering: fall 2017 to spring 2018
  • Public information meeting #2: late summer 2018
  • Final engineering: spring 2018 to fall 2018
  • Construction: spring 2019 to fall 2019